Most homeowners expect the hard part of a water loss to be the water. It usually is not. The fans and dehumidifiers tend to go well. The trouble starts after the equipment leaves, when the drying crew hands off to a repair crew and nobody owns the next step.
Below is a realistic timeline for a typical residential water loss in Central Texas, with the points where jobs usually stall and what to ask so yours does not.
The first hour: stop the damage
- Shut off the water at the source or the main if it is safe.
- Keep people away from wet electrical outlets, sagging ceilings, and any water that may be contaminated.
- Take photos before anything is moved.
- Call a restoration company that answers 24/7. TRG's average arrival across Greater Austin is under 60 minutes.
For more on first steps, see what to do after a kitchen flood and what to do after a flooded bathroom.
Day 1: extraction, mapping and setup
A good crew does four things on day one:
- Extracts standing water.
- Classifies the water. Category 1 is clean, Category 2 is significantly contaminated, Category 3 is grossly contaminated, like sewage or floodwater. The category decides what can be saved.
- Maps moisture with thermal imaging and moisture meters, including inside walls and under flooring.
- Removes materials that cannot be dried, such as wet insulation or swollen baseboards, and sets drying equipment.
You should leave day one knowing what is wet, what is coming out, and why.
Days 2 to 5: drying and daily monitoring
Most clean-water losses in typical construction dry in roughly three to five days. Dense materials, hardwood, and Category 2 or 3 water take longer. The IICRC S500 standard is the industry framework for this work.
What should happen every day:
- A technician checks the equipment.
- Moisture readings are taken on the same spots and logged.
- Photos are added to the job file.
What should not happen: equipment left running for days with no readings. If nobody is measuring, nobody knows when you are dry, and you may be paying for equipment days you did not need. Our guide on how long water damage takes to dry goes deeper on drying times.
Drying complete: the handoff
Equipment comes out when the readings hit the drying goal for each material, not on a fixed day. You should get the drying record: readings, photos, and a list of what was removed. Your adjuster needs the same file.
This is where most bad reviews begin. In the 1 to 3 star Google reviews we read for six Austin restoration companies, the most common complaint was the same story: mitigation went fast, then the repair side went quiet. Customers described a new project manager, unanswered calls, and repair timelines that ran far past the quote.
Ask before the fans leave:
- Who is my contact for repairs, and how often will I hear from you?
- When will I see the repair estimate?
- Has the drying file been sent to my adjuster?
Weeks 1 to 3: repair estimate and insurance approval
The repair estimate is written from the mitigation file. If you have a claim, the adjuster reviews it, and there may be a back and forth on line items. Time here depends mostly on the carrier.
Keep it moving:
- Ask for a copy of everything sent to your adjuster.
- Respond to the adjuster quickly. Many delays are a missing signature or photo.
- Approve the scope in writing before work starts.
Repairs: drywall, flooring, cabinets, paint
Repair time depends on four things:
- How much was removed.
- Material lead times. Flooring and cabinets are the usual long poles.
- Trade schedules: drywall, paint, flooring, plumbing.
- Changes you make, such as upgrades.
A small drywall and paint repair can be done in days. A kitchen with cabinets and flooring can take weeks. A good contractor gives you a written schedule once the scope is approved and tells you when a date moves, before you have to ask.
Final walkthrough and closeout
At the end you should walk the job with the contractor, get a punch list fixed, and receive your final documents: photos, drying records, invoices, and any certificates. Keep them with your property records.
How TRG handles the handoff
TRG documents every water job from day one, with photos and moisture readings in the job file and end-of-day updates from the crew. Our office team and Operations Manager stay with your job from the first call to the final walkthrough, and you hear from us at least every 48 hours and any time the scope changes. The drying file, the repair scope, and the reconstruction work stay under one company, so nothing gets lost in a handoff.